What is a WIP limit?

A WIP (work in progress) limit caps how many items can be in a stage of a Kanban board at once, so the team finishes work before starting more.

When a column reaches its limit, nobody pulls new work into it; instead people help finish what is already there. This exposes bottlenecks and shortens cycle time, because work spends less time waiting.

Choosing a limit

A common starting point is one or two items per person in a stage, adjusted after a few weeks. If the limit is never hit it is too high; if work constantly stalls it may be too low.

Example

A support team sets a limit of 4 on "In review". When the column is full, developers review tickets before picking up new ones.