What is the critical path?

The critical path is the longest chain of dependent tasks in a project; any delay to a task on it delays the whole project.

Tasks on the critical path have no slack. Tasks off it can slip a little without moving the end date. Knowing the difference tells a project manager where to focus attention and extra help.

Example

Design (5 days) blocks build (10 days), which blocks testing (4 days): 19 days. Writing documentation (6 days) can run in parallel, so it is not critical.